College Green plaza redevelopment budget soars to €80m – The Irish Times


AI Summary Hide AI Generated Summary

Project Overview

The redevelopment of Dublin's College Green plaza has seen its budget skyrocket to €80 million, a €70 million increase from the initial proposal eight years ago. This substantial cost increase is accompanied by significant delays, with completion unlikely before the end of the decade.

Initial Proposal and Setbacks

In 2017, Dublin City Council submitted a €10 million plan for a pedestrian and cycle plaza. However, An Bord Pleanála rejected the application in 2018 due to concerns about negative impacts on bus services.

BusConnects and Reshaped Plans

The National Transport Authority's (NTA) BusConnects plan, published in 2020, proposed rerouting buses away from College Green, resolving the previous conflict. This change allowed the council to expand the plaza's size significantly.

Cost and Timeline

The project's €80 million budget includes a substantial contingency fee of approximately 40%. The timeline remains uncertain, dependent on the completion of rerouting buses (expected by the end of 2026) and whether a planning application to the Coimisiún Pleanála is necessary (adding at least 12 months). Construction could take up to three years once it begins.

Funding and Collaboration

The NTA will contribute to the project's cost, although the exact amount remains undetermined. The council aims to complete preliminary designs by the end of summer 2024, following which a screening process will determine the next steps.

Sign in to unlock more AI features Sign in with Google

The budget for Dublin’s College Green civic plaza has soared to €80 million, an increase of €70 million since the scheme was last submitted for planning permission eight years ago.

The project to create a traffic-free plaza is also facing additional lengthy delays with completion unlikely before the end of this decade, Dublin City Council officials have said.

In May 2017 the council submitted an application to An Bord Pleanála for a €10 million pedestrian and cycle plaza. In November 2018 the board refused permission citing the potential for “significantly negative impacts” on bus services.

The National Transport Authority (NTA) in September 2020 published its final plans for a redesigned bus network for the city. Under BusConnects, services would be routed away from College Green and east Dame Street.

With the conflict with bus services removed, the council decided to double the size of the plaza. Traffic would be banned from the area west of the Luas lines in front of Trinity College, extending as far as the junction with Dame Street and South Great George’s Street.

Architect image of the proposed new College Green plaza
Under BusConnects, bus services will be routed away from the College Green area. Photograph: Dara Mac Donaill

Two years later the council announced a new design team was required due to increases in the scope of the project.

In a briefing to councillors in recent weeks, the scheme’s project manager Marie Gavin said she hoped “preliminary designs” would be completed by the end of the summer. These designs would then be subject to a “screening process” to determine whether the project could be progressed through the council’s internal planning system or if an application to An Coimisiún Pleanála, the new name for the reconstituted An Bord Pleanála, was required.

Cost was “a big factor” she said. “It is a big project so it’s going to cost a lot of money.”

The project had been approved for a budget of “about €80 million” that would be part funded by the NTA. That included a “huge contingency fee” of “about 40 per cent” but that should “hopefully cover everything we have to do” she said.

The timeline for the project would depend on whether an application to the Coimisiún was required, which would add “at least 12 months, minimum” but also on the removal of the bus routes, now scheduled to happen by the end of 2026.

“Realistically we’re looking at about October/ November 2027 to be on site with the project, with the best will in the world, and then it could be up to a three-year construction period.”

A spokesman for the NTA said it expected to complete rerouting of buses from the plaza area by the end of next year. The NTA will make a contribution to the cost of the project, but the level of that contribution has not yet been determined, he said.

Was this article displayed correctly? Not happy with what you see?

We located an Open Access version of this article, legally shared by the author or publisher. Open It
Tabs Reminder: Tabs piling up in your browser? Set a reminder for them, close them and get notified at the right time.

Try our Chrome extension today!


Share this article with your
friends and colleagues.
Earn points from views and
referrals who sign up.
Learn more

Facebook

Save articles to reading lists
and access them on any device


Share this article with your
friends and colleagues.
Earn points from views and
referrals who sign up.
Learn more

Facebook

Save articles to reading lists
and access them on any device