Appleton airport expands ahead of 2025 NFL Draft


AI Summary Hide AI Generated Summary

Appleton Airport Expansion for 2025 NFL Draft

Appleton International Airport (ATW) in Wisconsin is expanding its concourse for $70 million to handle an expected 30,000 passengers during the 2025 NFL Draft. The project, funded by various federal, state, and local sources, includes new gates, boarding bridges, restrooms (including sensory and service animal relief areas), and improved seating.

Project Timeline and Phases

  • Phase 1: Completion by April 30, 2025, includes three new gates.
  • Phase 2: April 24 - June 2025, connects existing and new concourses.
  • Phases 3 & 4: May - December 2025, further expansion and upgrades.

Construction by Miron Construction began in November 2024. Further airport improvements, including front drive lane expansion and ticket counter/baggage area upgrades, are planned post-draft.

Sustainability Initiatives

The expansion prioritizes sustainability, aiming for a 70% reduction in energy use and a 50% offset of energy consumption by 2030. Features include a white roof, low-flow fixtures, photovoltaic systems, and natural sunlight utilization. The airport also plans to install a geothermal system to further reduce its carbon footprint.

Financial Aspects

The $70 million cost is covered by multiple funding sources, including approximately $17 million from the Federal Aviation Administration, $10 million from Outagamie County, $7 million from the state of Wisconsin, and nearly $25 million from the airport itself.

Sign in to unlock more AI features Sign in with Google
Listen to this article

THE BLUEPRINT:

  • Appleton airport expects 30,000 passengers for 2025 NFL Draft
  • $70 million concourse expansion includes new gates, sensory rooms and restrooms
  • Project will bid for photovoltaic panels to offset the building’s energy usage
  • Construction phases continue into 2026 with more upgrades underway

Expecting nearly 30,000 passengers during the 2025 NFL Draft, Appleton International Airport officials said the next phase of their $70 million concourse expansion will open ahead of the football event.

The airport will open the first phase of the concourse expansion before the NFL Draft, said Abe Weber, the airport director at Appleton International Airport. The project features new gate space, three new boarding bridges, new restrooms with a service animal relief area, multi-user restrooms, sensory rooms, a quiet room and new seating at the ATW Biergarten, he added.

“As soon as we open phase one, we’ll get started on phase two, connecting the existing concourse with the new concourse, that portion of the project should take us through the end of this year and into the first part of 2026,” Weber said.

Miron Construction won the bid and broke ground in November 2024. The project is a 60,000-square-foot extension of its current footprint with modern features to improve passenger experience and accessibility. With the airport hitting 10 boarding gates, Weber said this will be the busiest airport in northeast Wisconsin.

ATW will see 1,417 flights for the month in April, a 17% increase over April 2024, Weber said. When the NFL Draft arrives from April 23-27, there will be 272 flights and the airport expects nearly 30,000 passengers coming through its doors, he added.

Currently the concourse expansion cost is $70 million and was supported with more than 12 funding sources across federal, state and local programs, Weber said. The airport itself contributed nearly $25 million to the project. Other large contributors include the Federal Aviation Administration discretionary grant program with around $17 million, Outagamie County with a $10 million investment and the state of Wisconsin provided $7 million in funding.

After being selected by a sustainable pilot program in 2011, the airport has two sustainability goals to reduce energy use by 70% in its passenger terminal and to offset passenger terminal energy consumption by 50% by using renewable energy sources, said Theresa Lehman, the director of sustainable services at Miron. The airport wants to hit both goals by 2030 even as it continues to grow, she added.

The terminal has a 70% energy savings target compared to code compliant buildings and offsets energy use with a roof-mounted photovoltaic system, Lehman said. The rest of the building’s energy needs would be bought from offsite renewable resources, making it a Class D zero-emissions building, she added.

The ATW was given federal funding for a PV system, Lehman noted. The new addition will bid a roof-mounted PV system on April 17.

Sustainable features include a white roof to reduce the heat island effect, low flow plumbing fixtures, photovoltaic systems, use of natural sunlight and advanced ventilation systems. There are several WELL Building Feature additions such as live trees and indoor plantings to create a park-like setting, she added.

Mead & Hunt served as the LEED project administrator and commissioning agent to help deliver sustainable features. Miron also had a goal to divert 75% of construction and demolition debris from the landfill.

The first phase of concourse expansion is expected to wrap up by April 30, which includes three new gates for NFL Draft attendees, Lehman said. The second phase will start April 24 and will be completed in June 2025, she added.

Phase three will start in May and will be completed by December 2025, Lehman said. Phase four will start in October and will be completed by December 2025.

As part of a sustainability master plan goal to reduce energy use in the passenger terminal by 70% in five years, the airport’s next goal is to install a vertical, closed-loop geothermal borefield for the passenger terminal, Lehman noted.

The geothermal system would produce roughly 1.3 million kilowatt hours each year for cooling and around 1.5 million kWh per year for heating, Lehman said. Through the EPA Greenhouse Gas Equivalencies Calculator, the project would lift 1,984 metric tons of carbon dioxide, which is equal to more than 400 cars driven each year or for more than 4.9 million miles, Lehman noted.

And construction will continue for other parts of the airport after the NFL Draft. Weber said additional projects will expand ATW’s front drive lanes and the airport is designing an expansion to ticket counters and outbound baggage areas.

Outside at the future airport terminal. The aggressive extension includes 60,000 square feet of new airport space with sustainable and inclusive features. The $70 million project includes federal, local and state funding and money from the airport itself. (Photo courtesy of Appleton International Airport)

Was this article displayed correctly? Not happy with what you see?

Tabs Reminder: Tabs piling up in your browser? Set a reminder for them, close them and get notified at the right time.

Try our Chrome extension today!


Share this article with your
friends and colleagues.
Earn points from views and
referrals who sign up.
Learn more

Facebook

Save articles to reading lists
and access them on any device


Share this article with your
friends and colleagues.
Earn points from views and
referrals who sign up.
Learn more

Facebook

Save articles to reading lists
and access them on any device